Project Schedule
The planned project schedule is outlined below. Please note that this schedule may change as the project progresses; in that case this page will be updated accordingly.
Milestone |
Date |
Status |
Notice of Intent Published to Federal Register |
17 Nov 23 |
Complete |
Scoping Period (30 Days) |
17 Nov - 16 Dec 23 |
Complete |
Prepare Draft (D) EIS/OEIS and conduct internal reviews |
Sep 23 - Sep 24 |
Complete |
Release DEIS/OEIS to the public |
Sep 24 |
Complete |
DEIS/OEIS public comment period (60 days) |
20 Sep - 21 Nov 24 |
Complete |
Public Meetings |
07 - 25 Oct 24 |
Complete |
Prepare FEIS/OEIS and conduct internal reviews |
Nov 24 - Aug 25 |
Complete |
Notice of Availability of Final Supplemental EIS/OEIS |
Aug 25 |
Complete |
30 Day Wait Period |
Aug - Sep 25 |
In Progress |
Record of Decision Signed |
Sep 25 |
Pending |
Blue Text = Complete |
Green Text = In Progress |
Dark Grey Text = Pending / Not Started |