Project Schedule
The planned project schedule is outlined below. Please note that this schedule may change as the project progresses; in that case this page will be updated accordingly.
| Milestone |
Date |
Status |
| Notice of Intent Published to Federal Register |
17 Nov 23 |
Complete |
| Scoping Period (30 Days) |
17 Nov - 16 Dec 23 |
Complete |
| Prepare Draft (D) EIS/OEIS and conduct internal reviews |
Sep 23 - Sep 24 |
Complete |
| Release DEIS/OEIS to the public |
Sep 24 |
Complete |
| DEIS/OEIS public comment period (60 days) |
20 Sep - 21 Nov 24 |
Complete |
| Public Meetings |
07 - 25 Oct 24 |
Complete |
| Prepare FEIS/OEIS and conduct internal reviews |
Nov 24 - Aug 25 |
Complete |
| Notice of Availability of Final Supplemental EIS/OEIS |
15 Aug 25 |
Complete |
| 30 Day Wait Period |
Aug - Sep 25 |
Complete |
| Record of Decision Signed |
09 Oct 25 |
Complete |
| Blue Text = Complete |
Green Text = In Progress |
Dark Grey Text = Pending / Not Started |