Project Schedule


The planned project schedule is outlined below. Please note that this schedule may change as the project progresses; in that case this page will be updated accordingly.  

Milestone Date Status
Notice of Intent Published to Federal Register 17 Nov 23 Complete
Scoping Period (30 Days) 17 Nov - 16 Dec 23 Complete
Prepare Draft (D) EIS/OEIS and conduct internal reviews Sep 23 - Sep 24 Complete
Release DEIS/OEIS to the public Sep 24 Complete
DEIS/OEIS public comment period (60 days) 20 Sep - 21 Nov 24 Complete
Public Meetings 07 - 25 Oct 24 Complete
Prepare FEIS/OEIS and conduct internal reviews Nov 24 - Aug 25 Complete
Notice of Availability of Final Supplemental EIS/OEIS Aug 25 Complete
30 Day Wait Period Aug - Sep 25 In Progress
Record of Decision Signed Sep 25 Pending
Blue Text = Complete Green Text = In Progress Dark Grey Text = Pending / Not Started